Multi Phase project that consisted of 3 years to complete. New construction steam line was installed underground to serve as an upgrade to the existing steam system.  New lighting, ventilation system, controls, and dewatering.  Worked with engineering on 40, 60, 100% design to final IFC for construction.

Power outages were required in multiple building to supply primary needs to tunnel. This required no disruption in client production of services.  Temporary lighting / power and was installed thru the building interior for continuation of steam system upgrade. Multiple of other projects were completed during the contract form trailer relocation, PIV valve commissioning and wiring, relocating and removing electrical for project continuation.

Prime: Greenberry